Laying of Synthetic Hockey Turf at Gilgit

  1.  

Name of project

 

Laying of Synthetic Hockey Turf at Gilgit

(Prime Minister’s directive)

  1.  

PM’s Directive No.

No.F.3(18)/Annou-PM/G-II/PAW/05 dated 25-10-2005

  1.  

Location

Lalik Jan Stadium, Satellite Town, Jutial, Shahrah-e- Quid-e-Azam, Gilgit

  1.  

Owner of Land

Gilgit-Baltistan Administration

  1.  

Land available

25 Kanal

  1.  

Estimated Cost

Rs.  35.807 million (Original)

Rs.  58.143 million (Revised)

Rs.123.713 million (2nd Revision)

  1.  

Date of approval

17-03-2007 (Original)                     DDWP          

17-05-2010 (Revised)                    DDWP

24-05-2018 (2nd Revision)              CDWP

  1.  

Date of Admn. approval

20-03-2007 (Original)

14-05-2011 (Revised)

06-08-2018 (2nd Revision)

  1.  

Executing agency

Pakistan Sports Board (PSB)

  1.  

Project Director

Director General, PSB

  1.  

Allocation in      2006-07

                        2007-08

                        2008-09

                        2015-16

                        2016-17

                        2017-18

                        2018-19

                        2019-20

Rs.20.000    million

Rs.10.307    million

Rs.00.825    million

Rs.02.000    million

Rs.02.000    million

Rs.15.000    million

Rs.102.183  million

Rs.102.183  million

Total: Rs.254.498 million

 

  1.  

Releases

 

 

 

2006-07

No.F.3-(23)/2006-P&D dated 30-03-2007

2007-08

No.F.3-(23)/2006-P&D dated 10-11-2007

No.F.3-(23)/2006-P&D dated 24-03-2008

2008-09

No.F.3-(23)/2006-P&D dated 29-09-2008

 

 

Rs.20.000    million

 

Rs.10.111    million

Rs.00.196    million

 

Rs.00.825    million

Total: Rs.31.132 million

 

  1.  

Expenditure Made

 

Rs.21.530 million

  1.  

Funds deposited in Government Treasury

(2010-11)

 

Rs.9.602 million

  1.  

Facilities

 

  • Synthetic Hockey Turf
  • Pavilion
  • Seating Steps
  • Sub Base
  • E-Layer
  • RCC Drain with Drain Covers
  • Fencing around Hockey Field
  • Pump House
  • Cutting, leveling & Filling of Ground
  • Electrification (External)
  • Underground Water Tank 15000 Gallons
  • Tough Pavers Around Hockey Field
  • Disposal of Sewerage & Rainy Water
  • Retaining Wall & Earth Filling