Boxing Gymnasium, Karachi
|
Name of project |
Construction of Boxing Gymnasium at Karachi (President’s Directive)
|
|
Location |
PSB Coaching Centre, Sir Shah Suleman Road, Karachi
|
|
Approved Cost |
Rs.39.595 million (Original) Rs.76.747 million (Revised) Rs.133.671 million (2nd Revision) |
|
Approving authority |
DDWP CDWP CDWP |
|
Date of approval |
30-10-2004 03-11-2007 19-03-2018 |
|
Facilities |
Gymnasium, Seating, Changing Room/ Toilets, Kitchen, Conference/Press Room, Entrances, PA System and Compound Wall
|
|
Scope of work |
Playing Hall, wooden floor (120x80 Players changing rooms / toilets, Gym, Store, Offices & conference room, Spectators entrances, Spectators toilets, VIPs entrance, Spectators seats 1500 to 1800,VIPs enclosure and Camera platforms & commentator booth
|
|
Completion Period |
30 Months
|
|
Releases
|
Rs.90,024,582 |
|
Name of Consultant |
M/s Karrar Kazim Associates, Islamabad |
|
Name of Contractor |
M/s Z.A. Engineers, Islamabad |
|
Date of award of contract |
30-12-2004 (Original) 22-05-2019 (Revision-II) |
|
Cost of contract |
Rs. 34,578,919.00 (Original) Rs. 72,100,002.00 (Revision-I) Rs.126,068,393.00 (Revision-II) |
|
Date of agreement |
07-01-2005 (Original) 24-04-2009 (Revision-I) 23-05-2019 (Revision-II) |
|
Date of start of work |
10-01-2005 (Original) Revision-I |